Location
Geelong, VIC
Client
Barwon Water
Sector
Water Infrastructure
Completed
February 2025
Scope of Works
Replacement of corroded steel reinforcement with GFRP across six 38m clarifier tanks.
Challenges
Sequenced shutdowns to maintain potable water supply to 280,000 residents.
Outcomes
Doubled expected service life with significantly reduced lifecycle maintenance cost.
Reinforced concrete and FRP renewal of clarifier tanks and treatment infrastructure.